Update on the Building's Progress

Latest Construction Targets

On a site visit on 16 June, 2009, we saw the progress being made on the build and learned more about the schedule for the next two months…

Work to date includes:

  • Completion of the access road onto the site
  • Completion of the piling mat which consists of 450mm stone and forms a level field for the piling rig
  • Completion of 190 Continuous Flight Augered Piled foundations which consist of columns being drilled deep in to the ground and then filled with concrete to ensure a stable base for the building
  • Commencement of load testing of the piles

Work schedule for remainder of June into July includes:

  • Breaking down of the piles to a set level in preparation for the next stage of the ground works
  • Further excavation and concreting of the pile caps and ground beams (another form of foundations)
  • Following on from this the next stage will actually see the building moving out of the ground as the commencement of the four concrete core towers will begin, these will house the stairs and lifts for the building along with providing stability to the structure

Images From the momentum Site

  • Construction Site Image 1 – 17/6/09
  • Construction Site Image 2 – 17/6/09
  • Construction Site Image 3 – 17/6/09
  • Construction Site Image 4 – 17/6/09

Images taken on 16 June, 2009