Work this Month

  • Completion of the load testing to the pile foundations
  • Commencement of the ground beam foundations
  • Crawler crane brought to site
  • Commencement of concrete cores

Work Planned

The project is now in its 11th week and as you can see from the photographs below the works are now well underway. For the rest of July and in to the beginning of August we will carryout the following works:

  • Construction of the concrete cores. These cores will be six stories high, standing an impressive 24 metres tall. These cores provide the structural stability to the building along with housing the stairs and lifts to each floor.

Images From the momentum Site

  • Construction Site Image 1 – 14/7/09
  • Construction Site Image 2 – 14/7/09
  • Construction Site Image 3 – 14/7/09
  • Construction Site Image 4 – 14/7/09
  • Construction Site Image 5 – 14/7/09

Images taken on 14 July, 2009

Top of page…