November 2009 – Building Work Progress
We literally took our first steps in the studios. The first layer of concrete is completed and we able
to actually appreciate the scale of the building from within. The views from the top floor across Leeds
are quite stunning. The steel structure is scheduled to be completed over the next 2 weeks and then the
roof goes on during the second week of December. At the same time the internal structures of the
external walls are being installed.